Update – Work on the highway past Flaming Gorge

UDOT Resurfacing S.R. 44 in Daggett County
August 20, 2021

Schedule Update:
For the next two weeks, crews will add Saturdays to their schedule to make up for weather delays.

Schedule:
Tuesday – Thursday 6 a.m. – 5 p.m.
Friday 7 a.m. – 4 p.m.
Saturday 7 a.m. – 7 p.m.

Traffic Impacts: Alternating one-way traffic with flaggers and pilot car operations. Motorists can expect delays of up to 15 minutes. This project has a large trucking component to remove and replace the asphalt. Please be patient as we work to keep Utah moving!


Schedules are subject to change due to equipment issues or other unforeseen circumstances.
Project BackgroundThe Utah Department of Transportation (UDOT) has begun work to resurface S.R. 44 from Greendale Junction to milepost 14. Anticipated project completion is end of September 2021.
UDOT has activated a public information team for this project. Please use the information below for questions of concerns:
Hotline: (800) 292-3557 Email: martyasay@utah.gov